Recommendations / Transportation / Big Idea # 3: The Needle

Big Idea # 3: The Needle

Part of the "RENEW TROUP " initiative

TransportationLagrange/Troup $1,000,000+

Overview

The Needle is a proposed zero-emission public transportation system for LaGrange and Troup County. The plan recommends a small fixed-route transit system using fully electric buses or shuttles to connect the downtown core, LaGrange College, Lafayette Square, Sweetland Amphitheater, Wild Leap Brewery, and eventually additional routes across the community. The system is intended to be free to ride, supported by electric buses that can travel more than 45 miles on a charge and recharge in minutes.

Action plan

Short-term
Develop a transit plan within about 6 months; determine the location of a bus hub; begin fundraising and applying for federal/state grants within 1 year.
Medium-term
Purchase transit buses/shuttles and equipment; hire and train dispatch and transit drivers.
Long-term
Begin operations within 18 months; expand to additional routes as demand increases and the system becomes more viable over 3–5 years.

Expected impact

New Businesses Along RouteEconomic

Tracks the number of new businesses beginning along The Needle route.

Timeframe: Long-term
Initial Bus FleetInfrastructure

Tracks number of buses required for the proposed routing.

Projected: 6 Buses · Timeframe: Medium-term
Maintenance Facility Cost BenchmarkOperational

Tracks cost benchmark for a similar maintenance facility.

Projected: 1,800,000 Dollars · Timeframe: Medium-term
Downtown Activity and NightlifeCommunity

Tracks whether the shuttle advances downtown activity, evening use, and nightlife.

Timeframe: Long-term
Fixed-Route Transit System CreatedInfrastructure

Tracks whether a small fixed-route transit system is planned and implemented.

Projected: 1 Transit system · Timeframe: Short-term
Emissions ReductionSustainability

Tracks reduction in emissions, pollution, and traffic congestion.

Timeframe: Long-term
Foot Traffic at Drop-Off and Connecting HubsEconomic

Tracks increased pedestrian activity at stops and hubs.

Timeframe: Long-term
Route FrequencyOperational

Tracks proposed shuttle frequency in the downtown core.

Projected: 15 Minutes · Timeframe: Medium-term
Five-Year BudgetOperational

Tracks total five-year budget if implemented as proposed.

Projected: 6,734,000 Dollars · Timeframe: Long-term
Bus and Charging Infrastructure TotalOperational

Tracks combined cost of buses and charging infrastructure.

Projected: 5,234,000 Dollars · Timeframe: Medium-term
Bus Purchase CostOperational

Tracks estimated cost per bus.

Projected: 789,000 Dollars per bus · Timeframe: Medium-term
Charging Infrastructure CostOperational

Tracks estimated cost for charging infrastructure.

Projected: 550,000 Dollars · Timeframe: Medium-term
Electric Bus RangeOperational

Tracks capability of electric buses.

Projected: Over 45 Miles per charge · Timeframe: Medium-term
Destination ConnectivityInfrastructure

Tracks connections to major destinations such as downtown, LaGrange College, Lafayette Square, Sweetland Amphitheater, Wild Leap Brewery, and Great Wolf Lodge.

Timeframe: Medium-term
Annual Operations and Maintenance CostOperational

Tracks annual operating and maintenance cost for the bus fleet.

Projected: 300,000 Dollars per year · Timeframe: Long-term
RidershipInfrastructure

Tracks potential monthly ridership.

Projected: 20,000 Trips per month · Timeframe: Long-term
Free-to-Ride ServiceEquity

Tracks whether the transit service operates at no cost to riders.

Projected: 0 Rider fare cost · Timeframe: Long-term
Real Estate Value Near StopsEconomic

Tracks expected value increase for real estate close to regular stops.

Timeframe: Long-term

Key stakeholders

Federal Transit Authority Formula Funding through Georgia DOTGeorgia DOTCities/County, primarily LaGrange with initial routesCallaway FoundationSponsorships/AdvertisingElectric Transit Vehicle Institute (ETVI)Center for Transportation and the Environment (CTE)The RayLaGrange CollegeDowntown Development Authority / DDALaGrange City and/or Troup CountySweetland AmphitheaterWild Leap BreweryGreat Wolf LodgeThe Thread

Estimated budget

Capital/startup and operations/maintenance costs are identified. The proposed routing requires 6 buses at $789,000 each, plus $550,000 for charging infrastructure, totaling $5,234,000. A maintenance facility would also be needed; a similar facility in Seneca, SC cost $1,800,000. Operations and maintenance costs are estimated at $50,000 per bus per year, or $300,000 annually. The five-year proposed budget is $6,734,000. The plan notes that implementation can be scaled to meet funding constraints.